Solid Waste Management Facility
Application Review Sequence
- Pre-submission discussions with applicant.
- Application or submittal Received.
- (a) Within 15 day of receiving application, County Health Officer and applicant will be notified by DEQ – a copy will be sent to the applicant.
(b). Review by DEQ within 60 days of receipt of the application or submittal.
- Within the next 15 days:
- Informal discussion of inadequacies with applicant,
- Draft Notice of Deficiency (NOD) prepared and,
- NOD finalized by DEQ and sent to applicant
- Meeting to discuss NOD with applicant – optional at the discretion of the applicant.
- Response to NOD by applicant – within 90 days 17.50.513(1) ARM
- Within 15 days of receipt of the NOD response -- review and respond to any incomplete or inadequate items. Return to step 6 if necessary.
- Preparation of draft EA by DEQ or approval or denial of submittal – 30 days.
- Finalization of EA – Commence 30-day public comment period.
- Public meeting – optional.
- Review of public comments by DEQ – Within 15 days – Department will:
- Review comments,
- Request additional information from applicant as needed,
- Develop mitigations or permit conditions,
- Discuss these with applicant and,
- Finalize response and send to applicant and commentors.
- Decision by DEQ to license or not license the facility (or to recommend an EIS, which would put application on hold).
- Notify County Health Officer of DEQ decision to license facility.
- Within 15 days of DEQ decision to license, County Health Officer accepts or rejects DEQ decision.
- If County Health Officer rejects licensure decision, Appeal to Board of Environmental Review – 30 days.
- License granted or denied.